Constantine receives approval for Phase II: Underground Operation

On July 31 Constantine Metals Ltd. received the necessary permits to commence Phase II: Underground Exploration.

The plans were approved by three major entities. The Alaska Department of Environmental Conservation (ADEC) issued a Wastewater Management Permit. The Alaska Department of Natural Resources (ADNR) approved the Reclamation Plan. The Alaska Department of Mental Health Trust Land Office approved the overall Plan of Operations. 

Highlights of the plan include an underground ramp (tunnel) and two settling ponds while also the continuation of exploratory drilling, according to their Plan of Operations.

While the permits were approved by agencies, the plan may not become a reality. In order to proceed, Constantine requires unanimous approval from joint venture members (including Dowa), according to their news release. Constaintine must also acquire the necessary funds. According to Constantine’s Liz Cornejo, “it’s going to require a lot of capital,” as stated in Henry Leasia’s article.